Saltfleet Conservation Area Wetland Design (BC-1 and SC-5)

PROJECT: Saltfleet Conservation Area Wetland Design (BC-1 and SC-5)

CLIENT: Hamilton Region Conservation Authority

DESCRIPTION OF PROJECT:

  • Water’s Edge, with a team of sub-consultants (natural heritage, geotechnical, hydrogeological, and archaeology) completed a background review, field and desktop investigations, preliminary and final designs, and reports.
  • The detailed design includes construction plans and specifications with suitable detail for construction tendering purposes.
  • Two wetland storage facilities have been designed by Water’s Edge. BC-1 has been constructed. SC-5 has been designed and is undergoing review and approval.
  • Since each facility required a dam with a control structure, MNRF was also part of the review agency team for LRIA permits.

SERVICES PROVIDED: Geomorphic Assessment, Hydrology/Hydraulics, Detailed Design, Cost Estimation Approval Agency Coordination

DATE OF PROJECT: 2019-2024